14. During a certain period, 4,000 labour hours were utilized, and the standard hours for actual production were 5,500 hours. The Variable Overhead Efficiency Variance amounted to ` 15,000 (Favourable). Calculate the Standard Variable Overhead Rate per hour.
Options
A` 15 per hour
B` 20 per hour
C` 10 per hour
D` 25 per hour