Question Scenario
Nitesh Gupta is constructing his house. For this purpose, he entered in a contract with M/s Baba Brick House to supply of 10,000 bricks on 12th August 2023. M/s Baba Brick House has two Lorries of 5,000 brick capacity. On 12th August 2023, one of the Lorries was not in working condition so M/s Baba Brick House supplied only 5,000 bricks and promised Nitesh Gupta to supply rest 5,000 bricks on next day. Nitesh Gupta wants to cancel the contract, as M/s Baba Brick House did not supply the bricks as per the contract. M/s Baba Brick House gave the plea that no fault has been made from its part, hence contract should not be cancelled. In this situation, whether Nitesh Gupta can avoid the contract under Indian Contract Act, 1872?
Estimated Writing Time: 7 mins Try in Practice Mode