Question Scenario

On 1st March 2023, T Readymade Dress Garments, Shimla enters into a contract with J Readymade Garments, Jaipur for the supply of different sizes of shirts ‘S’ (Small), ‘M’ (Medium), and ‘L’ (Large). As per the terms of the contract, 300 pieces of each category i.e. ‘S’ @`900; ‘M’@ 1,000 and ‘L’ @ 1,100 per piece have to be supplied on or before 31st May, 2023. However, on 1st May, 2023, T Readymade Dress Garments, Shimla informed J Readymade Garments, Jaipur that the firm is not willing to supply the shirts at the above rate due to the rise of prices in the raw material cost. In the meantime, prices for similar shirts have gone up in the market to the tune of ` 1,000; `1,100; and ` 1,200 for ‘S’, ‘M’ and ‘L’ sizes respectively. Examine the rights of J Readymade Garments, Jaipur in this regard as per the provisions of the Indian Contract Act, of 1872.

Estimated Writing Time: 5 mins Try in Practice Mode

Suggested Answer

As per the provisions of Section 39 of the Indian Contract Act, 1872, when a party to a contract has refused to perform, or disabled himself from performing, his promise in its entirety, the promisee may put an end to the contract, unless he has signified, by words or conduct, his acquiescence in its continuance. J Readymade Garments in the given situation has two options, out of which he has to select any one: i) Either to treat the contract as rescinded and sue T Readymade Dress Garments for damages from breach of contract immediately without waiting until the due date of performance or ii) He may elect not to rescind but to treat the contract as still operative and wait for the time of performance and then hold the other party responsible for the consequences of non performance. Important Note: The answer can also be given as per Section 73 of the Indian Contract Act, 1872 which lays down that when a contract has been broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract, compensation for any loss or damage caused to him thereby which naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach of it. In the instant case, J Readymade Garments, Jaipur would be entitled to get the damages i.e. difference between the contract price and the market price on the day of default from T Readymade Dress Garments, Shimla. In other words, the amount of damages would be ` 90,000 [300 piece @ ` 100 (Small), 300 piece @ ` 100 (Medium) and 300 piece @ ` 100 (Large)].

Exam Strategy Tip

When answering law questions in the CA Foundation exam, follow the "Provision -> Facts -> Conclusion" structure for maximum marks. Ensure to state the relevant sections where applicable to earn bonus marks from the evaluator.

Ready to Practice More Law Cases?

Test your knowledge under timed conditions in our dedicated Writing Practice Mode. Get a feel for the real exam pressure.

Enter Writing Practice