Question 5 (a) The following information has been provided by a company: Number of units produced and sold : 7,000 Standard labour rate per hour : ₹ 9 Actual hours worked : 17,820 hours Labour efficiency : 106.8% Labour rate variance : 71,280 (A) You are required to calculate : (i) Actual labour rate per hour (1 Marks) (ii) Standard hours required for 7,000 units (2 Marks) (iii) Labour Efficiency variance (1 Marks) (iv) Standard labour cost per unit (1 Marks) (v) Actual labour cost per unit (1 Marks) (b) Journalise the following transactions assuming that cost and financial accounts are integrated: (4 Marks) Particulars Amount (in `) Wages paid (20% indirect) 2,00,000 Selling and Distribution Overheads incurred 50,000 Deficiency found in stock of Raw Material (Normal) 80,000 Factory Overheads (Under Absorbed) 60,000 (c) Define spoiled work and defective work and discuss the treatment of defective work in the following circumstances: (1 + 3 Marks) Circumstances Treatment Where a percentage of defective work is allowed in a particular batch as it cannot be avoided. Where the defect is due to bad workmanship Where defect is due to the Inspection Department wrongly accepting incoming material of poor quality.

For any discrepancies in this question, email contact@cadada.in

Detailed Solution & Explanation

(a) (i) Actual Hours Worked 17,820 Standard Rate Per hour 9 Labour Rate Variance 71280 (A) COST AND MANAGEMENT ACCOUNTING Labour Rate Variance = (Standard Rate – Actual Rate) Actual Hours (9 – Actual Rate) 17,820 = -71,280 (9 – Actual Rate) = - 4 Actual Rate = 13 (ii) Labour Efficiency = Standard Hours x 100  Actual Hours 106.8% = Standard Hours 1  7,820 Standard Hours = 19,031.76 (iii) Labour Efficiency Variance = (Standard Hours – Actual Hours) x Standard Rate = (19,031.76 – 17,820) x 9 = 10,905.84 (F) (iv) Standard Labour Cost per unit= 19,031.76 x 9  7,000 = 24.47 (v) Actual Labour cost per unit = 17,820 x 13  7,000 = 33.09 (b) Journal Entries under Integrated system of accounting Particulars (`) (`) (i) Work-in Progress Ledger Control A/c Dr. 1,60,000 Factory Overhead control A/c Dr. 40,000 To Wages Control A/c 2,00,000 (Being allocation of Direct and Indirect wages) (ii) Wages Control A/c Dr. 2,00,000 To Bank A/c 2,00,000 (Being wages paid) (iii) Cost of Sales A/c Dr. 50,000 To Selling & Distribution Overhead Control A/c 50,000 (Being selling & distribution overhead allocated) (iv) Selling & Distribution Overhead Control A/c Dr. 50,000 To Bank A/c 50,000 (Being selling & distribution overhead paid) (v) Factory overhead control A/c Dr. 80,000 To Stores Ledger Control A/c 80,000 (Being normal deficiency found in stock of raw material) (vi) Costing Profit & Loss A/c Dr. 60,000 To Factory Overhead Control A/c 60,000 (Being transfer of under absorption of factory overhead) (c) Spoiled work is the quantity of production that has been totally rejected and cannot be rectified. Defective work refers to production that is not as perfect as the saleable product but is capable of being rectified and brought to the required degree of perfection provided some additional expenditure is incurred Circumstances Treatment Where a percentage of defective work is allowed in a particular batch as it cannot be avoided. If the actual number of defectives is within the normal limit or is near thereto the cost of rectification will be charged to the whole job and spread over the entire output of the batch. If, on the other hand, the number of defective units substantially exceeds the normal, the cost of rectification of the number which exceeds the normal will be written off as a loss in the Costing Profit and Loss Account. Where the defect is due to bad workmanship. In this case cost of rectification will be abnormal cost and shall be written off as a loss. However, if the management did provide for a certain proportion of defectives on account of bad workmanship as an unavoidable feature of production. If that be the case, the cost COST AND MANAGEMENT ACCOUNTING of rectifying to the extent provided for by the management will be treated as a normal cost and charged to the batch. Where defect is due to the Inspection Department wrongly accepting incoming material of poor quality. In this case the cost of rectification will be charged to the department and will not be considered as cost of manufacture of the batch. Being an abnormal cost, it will be written off to the Costing Profit and Loss Account.

Key Concepts to Understand

More Questions from Cost and Management Accounting

Ready to Master Cost and Management Accounting?

Practice all 249 questions with instant feedback, earn XP, track your streaks, and ace your CA Foundation exam.

Start Practicing — It's Free